Greening the Big Box

Project Description & Outcomes

This project involved multiple components including an iron enhanced sand filter, tree trenches, and a raingarden/drainage swale.

The project was completed in partnership with Target, the City of Forest Lake, and the Comfort Lake-Forest Lake Watershed District.

big box

Project Status

Completed

Project Outcomes

9 lbs/yr phosphorus removal at edge of project

4 lbs/yr phosphorus removal at Comfort Lake

4,500 lbs/yr sediment removal edge of project

Financials

Clean Water Fund Grant: $176,047 

CLFLWD Grant Match: $70,419 

Total Project Budget: $246,466 

Timeline

2014: Project construction