East Comfort Pond Project
Project Description & Outcomes
This project will cleanout and expand an existing stormwater pond. It will capture and remove phosphorous from an adjacent 8-acre developed residential drainage area. The project will remove approximately 5.0 lbs./yr total phosphorus. The Comfort Lake-Forest Lake Watershed District is partnering with the City of Wyoming to implement this project.
Project Status
In-Progress
Project Outcomes
5 lb/yr phosphorus removal
Financials
Clean Water Fund Green Infrastructure Grant: $225,800
CLFLWD Grant Match: $22,580
Total Project Budget : $248,380
Lifecycle cost:
$1,200 per pound of phosphorus removed
Timeline
2025-2026: Project development and design
2026-2027: Project construction